NPRR092
| Title: |
Remove Voltage Schedules Requirement |
| Next Group: |
|
| Next Step: |
|
| Status: |
Approved on 04/15/2008 |
| Related Issue: |
|
| Related Project: |
|
| Date |
Gov Body |
Motion |
Result |
Against |
Abstentions |
| 04/04/2008 |
TAC
|
To recommend approval of NPRR092 as recommended by PRS. |
Passed |
0 |
0 |
| 03/20/2008 |
PRS
|
To forward the Recommendation Report and IA to TAC. |
Passed |
0 |
0 |
| 02/21/2008 |
PRS
|
To recommend approval of this NPRR based upon ROS comments and as revised by PRS. |
Passed |
1 IPM |
|
Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.
| Status: |
Approved |
| Date Posted: |
12/14/2007 |
| Sponsor: |
John Adams, ERCOT |
| Urgent: |
No |
| Sections: |
6.5.7.1.13, Data Inputs and Outputs for the Real-Time Sequence and SCED |
| Description: |
This Nodal Protocol Revision Request (NPRR) will remove the requirement for ERCOT to post hourly voltage schedules on the MIS Secure Area. |
| Reason: |
ERCOT systems do not generate or receive voltage schedule data. ERCOT does not normally provide voltage set point instructions to generators. ERCOT has delegated this responsibility to Transmission Operators (TOs). In order for this data to be provided to the market, a separate tool will need to be built in order to access the information from the TOs. |
-
(04/16/08, .doc, )
-
(04/04/08, .doc, )
-
(03/24/08, .doc, )
-
(03/14/08, .doc, )
-
(02/25/08, .doc, )
-
(02/20/08, .doc, )
-
(02/07/08, .doc, )
-
(01/29/08, .doc, )
-
(01/29/08, .doc, )
-
(01/29/08, .xls, )
-
(12/14/07, .doc, )