NPRR096
| Title: |
Revisions to the RMR Startup Energy Payment |
| Next Group: |
|
| Next Step: |
|
| Status: |
Approved on 03/18/2008 |
| Related Issue: |
|
| Related Project: |
|
| Date |
Gov Body |
Motion |
Result |
Against |
Abstentions |
| 03/18/2008 |
Board of Directors
|
Approve NPRR096 as recommended by TAC. |
Passed |
|
|
| 03/06/2008 |
TAC
|
To recommend approval as recommended by PRS. |
Passed |
0 |
0 |
| 02/21/2008 |
PRS
|
To forward the Impact Analysis and Recommendation Report to TAC. |
Passed |
0 |
0 |
| 01/17/2008 |
PRS
|
To recommend approval of this NPRR as submitted. |
Passed |
0 |
0 |
Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.
| Status: |
Approved |
| Date Posted: |
|
| Sponsor: |
ERCOT Staff |
| Urgent: |
No |
| Sections: |
6.6.6.2, RMR Payment for Energy |
| Description: |
This Nodal Protocol Revision Request (NPRR) incorporates language from the COMS Eligibility Process for Settlements Requirements (B2) (v3.0) (Eligibility Process) document approved by the Transition Plan Task Force (TPTF) on October 8, 2007. The proposed language is consistent with the language in the Eligibility Process to determine if a Reliability Must Run (RMR) Unit is to be compensated for its startup costs as well as Protocol Sections 5.6.2, RUC Startup Cost Eligibility, and 5.6.3, Forced Outage of a RUC-Committed Resource. |
| Reason: |
The Nodal Protocols need provisions for the determination of eligibility for compensation for startup costs in the event of multiple starts in a day from the Day Ahead Market (DAM) and Reliability Unit Commitment (RUC) markets. |
-
(03/18/08, .doc, )
-
(03/07/08, .doc, )
-
(02/25/08, .doc, )
-
(02/14/08, .doc, )
-
(01/22/08, .doc, )
-
(12/20/07, .xls, )
-
(01/07/08, .doc, )