NPRR101
| Title: |
Modify Time Requirements for Entry of Equipment in the Outage Scheduler |
| Next Group: |
|
| Next Step: |
|
| Status: |
Approved on 04/15/2008 |
| Related Issue: |
|
| Related Project: |
|
| Date |
Gov Body |
Motion |
Result |
Against |
Abstentions |
| 04/04/2008 |
TAC
|
To recommend approval of NPRR101 as recommended by PRS. |
Passed |
0 |
0 |
| 03/20/2008 |
PRS
|
To forward the Recommendation Report and IA to TAC. |
Passed |
0 |
0 |
| 02/21/2008 |
PRS
|
To recommend approval of this NPRR as revised by Luminant and AEP comments. |
Passed |
1 IPM |
|
Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.
| Status: |
Approved |
| Date Posted: |
02/06/2008 |
| Sponsor: |
Trip Doggett on behalf of the Transition Plan Task Force (TPTF) |
| Urgent: |
No |
| Sections: |
3.10.7.5.1, Continuous Telemetry of the Status of Breakers and Switches |
| Description: |
This Nodal Protocol Revision Request (NPRR) increases the time window from one minute to 30 minutes for requiring entries of equipment outages in the Outage Scheduler. |
| Reason: |
Current Nodal Protocol language would increase the number of scheduled Outages by over 20% by requiring the entry of all supplemental devices that must be operated to switch transformers (main power, standby, autotransformer and distribution Load), generators, and transmission lines in and out of service, into the ERCOT Outage Scheduler. This increase would place a burden on and add complexity and possible confusion for the following (1) TSPs and Resources who enter Outages; (2) ERCOT Outage Coordinators who must study and approve all Outages; and (3) Real-Time Operators who must monitor and enter actual Outage times. There will also be additional impacts on the Congestion Revenue Right (CRR) process.
This NPRR would significantly reduce the additional number of required Outage entries and will reduce the increased complexity in the Outage scheduling process for all Entities. |
-
(04/16/08, .doc, )
-
(04/04/08, .doc, )
-
(03/24/08, .doc, )
-
(03/19/08, .doc, )
-
(02/25/08, .doc, )
-
(02/21/08, .doc, )
-
(02/19/08, .doc, )
-
(02/19/08, .doc, )
-
(02/14/08, .doc, )
-
(02/11/08, .doc, )
-
(02/06/08, .xls, )
-
(02/06/08, .doc, )
|